Earthwork and volume computations are subtopic C of Surveying on the FE Civil exam, and they are mostly careful bookkeeping with cross sections: average two end areas, weight a middle one, add up grid cells, and keep cut and fill straight along a mass diagram.

The five problems below, all in US units, use the average end area and prismoidal methods, a borrow pit grid cell, a mass haul ordinate and a shrinkage allowance. Every answer is in cubic yards.

Where this sits: NCEES lists Surveying at 6-9 questions of the 110 on the FE Civil exam, and earthwork and volume computations is subtopic C of the area. NCEES does not publish question counts below that level.

The Volume Relationships These Problems Use

The FE Reference Handbook gives the end-area and prismoidal formulas; areas in ft2, lengths in ft, and 27 ft3 to a cubic yard.

5 Free Earthwork Volume Problems

Give yourself about three minutes for each one, roughly the pace of the exam, and work it on paper before you look at the solution.

Problem 1 — Average End Area Volume

Using the Average End Area method, areas at consecutive stations are \( A_1 = 90\,\mathrm{ft}^2 \) and \( A_2 = 150\,\mathrm{ft}^2 \) separated by \( L = 150\,\mathrm{ft} \). What is the volume \( (\mathrm{yd}^3) \)?

Figure for FE Civil practice problem 1 (Surveying)

Answer: A) \( 667\,\mathrm{yd}^3 \)

Step 1 – Identify given information:

ParameterValue
\( A_1 \)\( 90\,\text{ft}^2 \)
\( A_2 \)\( 150\,\text{ft}^2 \)
Station spacing \( L \)\( 150\,\text{ft} \)

Step 2 – Average End Area method (FE Handbook):
\( V = \dfrac{L(A_1 + A_2)}{2} \)
Convert ft\(^3\) to yd\(^3\) by dividing by 27.

Step 3 – Substitute and solve:
\( V = \dfrac{150(90 + 150)}{2} = \dfrac{150 \times 240}{2} = 18{,}000\,\text{ft}^3 \)
\( V = \dfrac{18{,}000}{27} = 666.7 \approx 667\,\text{yd}^3 \)

Step 4 – Answer:
The volume is approximately \( 667\,\text{yd}^3 \).
(B) \( 800\,\text{yd}^3 \) and (C) \( 900\,\text{yd}^3 \) overestimate the result.
(D) \( 1{,}333\,\text{yd}^3 \) is exactly twice the answer: it multiplies the length by the sum of the end areas instead of by their average.
Remember: \( 1\,\text{yd}^3 = 27\,\text{ft}^3 \).

Correct answer: (A)

Problem 2 — Fill with a Shrinkage Allowance

A project needs \( 1{,}000\,\mathrm{yd}^3 \) of compacted fill. If a shrinkage factor of \( 12\% \) is used (increase fill by this factor), what loose fill volume should be planned?

Figure for FE Civil practice problem 2 (Surveying)

Answer: D) \( 1{,}120\,\mathrm{yd}^3 \)

Step 1 – Identify given information:

ParameterValue
Required compacted fill\( 1{,}000\,\text{yd}^3 \)
Shrinkage factor\( 12\% \)

Step 2 – Shrinkage adjustment (FE Handbook):
Shrinkage means soil compresses when placed as fill, so you need more loose material:
\( V_{\text{loose}} = V_{\text{compacted}} \times (1 + \text{shrinkage}) \)

Step 3 – Substitute and solve:
\( V_{\text{loose}} = 1{,}000 \times (1 + 0.12) = 1{,}000 \times 1.12 = 1{,}120\,\text{yd}^3 \)

Step 4 – Answer:
You need \( 1{,}120\,\text{yd}^3 \) of loose fill to achieve \( 1{,}000\,\text{yd}^3 \) compacted.
(A) \( 774\,\text{yd}^3 \) applies the 0.88 factor twice and in the shrinking direction, \( 1{,}000 \times 0.88 \times 0.88 \).
(B) \( 880\,\text{yd}^3 \) subtracts the 12 per cent instead of adding it.
(C) \( 1{,}000\,\text{yd}^3 \) ignores shrinkage entirely.

Correct answer: (D)

Problem 3 — Prismoidal Volume

Prismoidal method: \( A_1 = 40\,\mathrm{ft}^2 \), \( A_m = 55\,\mathrm{ft}^2 \), \( A_2 = 70\,\mathrm{ft}^2 \), with \( L = 100\,\mathrm{ft} \). What is the volume \( (\mathrm{yd}^3) \)?

Figure for FE Civil practice problem 3 (Surveying)

Answer: D) \( 204\,\mathrm{yd}^3 \)

Step 1 – Identify given information:

ParameterValue
\( A_1 \) (end area)\( 40\,\text{ft}^2 \)
\( A_m \) (middle area)\( 55\,\text{ft}^2 \)
\( A_2 \) (end area)\( 70\,\text{ft}^2 \)
\( L \) (length)\( 100\,\text{ft} \)

Step 2 – Prismoidal formula (FE Handbook):
\( V = \dfrac{L(A_1 + 4A_m + A_2)}{6} \)
This method is more accurate than Average End Area because it accounts for the middle cross section.

Step 3 – Substitute and solve:
\( V = \dfrac{100(40 + 4(55) + 70)}{6} = \dfrac{100(40 + 220 + 70)}{6} = \dfrac{100 \times 330}{6} = 5{,}500\,\text{ft}^3 \)
\( V = \dfrac{5{,}500}{27} = 203.7 \approx 204\,\text{yd}^3 \)

Step 4 – Answer:
The prismoidal volume is approximately \( 204\,\text{yd}^3 \).
(A) \( 102\,\text{yd}^3 \) adds the three areas over 6 without giving the middle one its weight of 4, which returns exactly half the volume.
(B) \( 150\,\text{yd}^3 \) underestimates.
(C) \( 200\,\text{yd}^3 \) is the same \( 5{,}500\,\text{ft}^3 \) rounded off; \( 5{,}500/27 = 203.7 \), not 200.

Correct answer: (D)

Problem 4 — Borrow Pit Grid Cell

An excavation grid cell is \( 50 \,\mathrm{ft} \) \(\times\) \( 50 \,\mathrm{ft} \). Corner depths are \( 3.2 \,\mathrm{ft} \), \( 2.8 \,\mathrm{ft} \), \( 3.6 \,\mathrm{ft} \), and \( 3.0 \,\mathrm{ft} \). Using average corner depth, what is the excavation volume (\( \mathrm{yd}^{3} \)), nearest \( 1 \,\mathrm{yd}^{3} \)?

Figure for FE Civil practice problem 4 (Surveying)

Answer: C) \( 292\,\mathrm{yd}^{3} \)

Step 1 – Identify given information:

One 50 ft × 50 ft cell (\( A = 2500 \) ft\(^2\)); corner depths 3.2, 2.8, 3.6 and 3.0 ft.

Step 2 – Average corner depth:

$$d_{avg} = \dfrac{3.2+2.8+3.6+3.0}{4} = \dfrac{12.6}{4} = 3.15 \;\text{ft}$$

Step 3 – Volume and convert:

$$V = 2500(3.15) = 7875 \;\text{ft}^3 \qquad \dfrac{7875}{27} = 291.7 \approx 292 \;\text{yd}^3$$

Step 4 – Answer: \( 292 \) yd\(^3\). Remember the conversion: \( 1 \;\text{yd}^3 = 27 \;\text{ft}^3 \) — skipping it is the classic slip.

(A) \( 208\,\text{yd}^3 \) averages only three of the four corner depths while still dividing by four, giving 2.25 ft of average depth instead of 3.15 ft.

Correct answer: (C)

Problem 5 — Mass Haul Ordinate

Mass haul: Between stations, the net volumes are: 0-1: \( +200\,\mathrm{yd}^3 \) (cut), 1-2: \( -150\,\mathrm{yd}^3 \) (fill), 2-3: \( +100\,\mathrm{yd}^3 \) (cut), 3-4: \( -300\,\mathrm{yd}^3 \) (fill). What is the mass haul ordinate at station 3?

Figure for FE Civil practice problem 5 (Surveying)

Answer: B) \( +150\,\mathrm{yd}^3 \)

Step 1 – Identify given information:

IntervalNet Volume (yd\(^3\))Type
0-1\( +200 \)Cut
1-2\( -150 \)Fill
2-3\( +100 \)Cut
3-4\( -300 \)Fill

Step 2 – Mass haul ordinate concept (FE Handbook):
The mass haul ordinate at any station is the cumulative algebraic sum of cut (+) and fill (-) volumes from the starting station.

Step 3 – Substitute and solve:
Ordinate at Station 3 = sum of intervals 0-1, 1-2, and 2-3:
\( M_3 = (+200) + (-150) + (+100) = +150\,\text{yd}^3 \)

Step 4 – Answer:
The mass haul ordinate at station 3 is \( +150\,\text{yd}^3 \) (net excess of cut over fill).
(A) \( +50\,\text{yd}^3 \) omits the third interval.
(C) \( -150\,\text{yd}^3 \) has the wrong sign.
(D) \( -250\,\text{yd}^3 \) includes the 3-4 interval, which is beyond station 3.

Correct answer: (B)

Three Mistakes That Cost Points

Frequently Asked Questions

Which is more accurate, average end area or prismoidal?

The prismoidal formula, because it uses a measured middle section. The average end area method usually overestimates the volume when the end areas differ a lot, but it is simpler and widely used for routine estimates.

What is the difference between swell and shrinkage?

Swell is the increase in volume when bank material is excavated and loosened. Shrinkage is the decrease when it is compacted in a fill. Read how the problem applies the percentage before you use it.

What does a mass haul diagram show?

The cumulative earthwork volume along the alignment. Rising parts are cut, falling parts are fill, and a horizontal line across the curve marks a balanced haul between two stations.

Keep Going

Practice the rest of the area on the FE Civil surveying practice problems page, or keep going with the area computation problems. To see these topics mixed with the other 13 areas, take the free FE Civil practice exam, or browse every topic in the free FE Civil practice problems hub.